Just now, Excalibur_GUI and Unit_Test_Excalibur_GUI area has total 70 p1 + p2 bugs.
Note: This 70 bugs not includes the bugs that will be fixed once sprint2 project finish - 17 bugs
Sprint2 Bug fix plan:
Week | Dev Resource | Plan Dev Fixed | Plan QA Logged | Bug Number (approximation) |
Apr. 24 - Apr. 24 | - | - | - | 70 |
Apr. 27 - Apr. 30 (4 days) | 1.5 | 2 * 1.5 * 4 = 12 | 3 * 4 = 12 | 70 |
May. 4 - May. 8 | 3 | 2 * 3 * 5 = 30 | 15 * 5 = 75 | 115 |
May. 11 - May. 15 | 10.5 | 2 * 10.5 * 5= 105 | 15 * 5 = 75 | 85 |
May. 18 - May. 22 | 10.5 | 2 * 10.5 * 5= 105 | 10 * 5 = 50 | 40 |
May. 25 - May. 29 (4 days) | 10.5 | 1 * 10.5 * 4 = 44 | 10 * 4 = 40 | ??? |
Dev Resource:
Resource | Apr. 27 - Apr. 30 | May. 4 - May. 8 | May. 11 - May. 15 |
Chunlin |
|
| 100% |
Gang |
|
| 100% |
Jiangwei | 100% | 100% | 100% |
Lin |
|
| 100% |
Liyuan | 50% | 100% | 100% |
Chao |
|
| 100% |
Fanbin |
|
| 50% |
Hong |
|
| 100% |
Peng |
| 50% | 100% |
Xiaodong |
|
| 100% |
Yong |
| 50% | 100% |
SubTotal # | 1.5 | 3 | 10.5 |
Note: The resource does not include Wanqing.